38 new licenses for wind farms in Almería

wind turbines

The Junta de Andalucía, through the Territorial Delegation of Economy, Innovation, Science and Employment of Almería, has in process 38 authorizations of several companies for the construction of 38 new wind farms in the province, where no installation of this type has been registered for five years.

According to various data transmitted by the Andalusian Administration, companies that wish to start up a wind farm have to obtain an authorization prior administrative, a construction authorization and an exploitation authorization before starting its operation.

Construction of the parts of a wind turbine

Thus, these 37 projects are still in progress. authorization phase prior administrative and one in the exploitation authorization phase.

Blades of a wind turbine

In fact, the most advanced project is the 'Los Balazos' wind farm, which plans to locate a total of 14 wind turbines in Serón with an installed power of 42 megawatts. This project has had an administrative construction authorization since the end of 2010, so it has had to obtain several extensions to renew the permits.

renewable jobs

From the Board, they have commented that both for the 'Los Balazos' project and for others it is "urgent" the construction of the Vera-Baza-Caparacena power line, in order to have connection points to pour the electrical energy produced by wind farms.

greenhouses cause deettification by overexploitation of water

As they have explained, “The investments and jobs associated with these projects are at risk if there are no such coupling points and the authorizations They have expiration dates, so it is urgent that the Ministry of Energy undertake the construction of this important infrastructure.

The territorial delegate of Economy, Miguel Ángel Tortosa, already pointed out last August that there were at least three electricity generation projects pending the execution of the Caparacena-Baza-La Ribina axis for its start-up, which would entail a higher investment to the three million euros and the joint production of 339 megawatts per year.

Unemployed since 2012

The total power installed in wind farms has been increasing in the last decade without there having been a cessation of activity in any of the active parks. Unfortunately, since 2012 there has been a stagnation in this progression with a total operating power of 511,3 megawatts of wind produced by 19 wind farms.

History of wind energy and the Mills

This power includes the power of isolated mini-wind installations, which is 37,46 kilowatts and an installation of consumption connected to the electricity grid with 10,5 kilowatts.

Forecasts

However, the forecasts of the Delegation of Economy in 2010 pointed out that the province would have 24 wind farms in operation that would add up to a total installed power of 650,65 megawatts on the horizon of 2011, which would allow to increase the total installed power by almost a third compared to the end of 2009.

According to the latest provincial report on energy infrastructures from the Andalusian Energy Agency, Serón is the municipality that has more wind farms, a total of six that add 208,5 megawatts installed. In relation to installed power, it is followed by Vélez-Rubio with two parks with 48,5 megawatts, Abla with two parks with 42,5 megawatts, Abrucena with two other parks with 40 megawatts, and Nacimiento with two and 24,65 megawatts of installed potency. The rest are located in Enix, Alboloduy, Turrillas, Tíjola and Las Tres Villas.

Installation of a windmill

Currently, wind farms produce enough energy to cover more than 700.000 inhabitants, at the same time avoiding the emission into the atmosphere of about half a ton of carbon dioxide, the equivalent of taking some 220.000 vehicles off the road.

Emissions of greenhouse gases

Start up

For putting in operation of a wind farm, in the first instance it is necessary to obtain an administrative authorization, which requires obtaining the connection point to the grid granted by the distributor or transporter, the favorable environmental opinion by the Territorial Delegation for the Environment and Spatial Planning, the report of conformity or opposition from the Delegation for the Environment and Spatial Planning in the area of ​​urban planning as well as the compliance of all public administrations, agencies, public service companies or services of general interest with affected goods.

Once the prior administrative authorization has been obtained, the construction authorization would have to be obtained, in which it is verified that the execution project complies with all the conditions imposed in the previous one. This can be requested from simultaneous to prior administrative authorization. Finally, the exploitation authorization would be requested once the park has been built.


Be the first to comment

Leave a Comment

Your email address will not be published. Required fields are marked with *

*

*

  1. Responsible for the data: Miguel Ángel Gatón
  2. Purpose of the data: Control SPAM, comment management.
  3. Legitimation: Your consent
  4. Communication of the data: The data will not be communicated to third parties except by legal obligation.
  5. Data storage: Database hosted by Occentus Networks (EU)
  6. Rights: At any time you can limit, recover and delete your information.